Final account
Construction contracts generally provide some mechanism for the final payment to be made to the contractor on completion of the works described in the contract. Generally this payment will be made at the end of the defects liability period providing that all patent defects have been rectified.
Preparing the final account is the process of calculating and agreeing any adjustments to the contract sum (the amount originally set out in the contract to be paid to the contractor for completion of the works) so that the amount of the final payment can be determined. The amount of the final payment is then set out in the final certificate (or final statement). It is possible for the final certificate to show that money is owed to the client, rather than due to the contractor.
Construction contracts may not specifically require the preparation of a final account, although they generally do require the contractor to provide all documents necessary for the adjustment of the contract sum within a specified time, and set out the time scale for and consequences of issuing the final certificate.
The contract sum may need to be adjusted for a number of reasons, including:
- Variations.
- Fluctuations.
- Prime cost sums.
- Provisional sums.
- Payments to nominated sub-contractors or nominated suppliers.
- Statutory fees.
- Payments relating to the opening-up and testing of the works.
- Loss and expense.
- Liquidated and ascertained damages.
- Contra claims imposed as a result of the contractor's operations (such as a third-party claim resulting from contractor negligence or contractual breach, for example, flooding a neighbour's property).
- The release of any remaining retention.
Agreeing the final account can be a complicated, time consuming and adversarial process, often resulting in disputes. The process can be made easier if adjustments to the contract sum are agreed as the project progresses rather than saving them up for the end. It is also beneficial if the client's quantity surveyor and the contractor's quantity surveyor work together on drafts of the final account before agreement is sought. It is preferable that a draft copy of the final account is signed off by the contractor as an 'in full and final settlement' prior to issue.
Agreement of the final account will allow the contract administrator to issue the final certificate. The final certificate is conclusive that all patent defects have been remedied, all adjustments to the contract sum have been agreed and all claims settled. Latent defects may still become apparent after completion of the contract and these may give rise to action for damages, for breach of contract or negligence.
Where proceedings have begun in relation to a dispute, the conclusiveness of the final certificate is subject to the findings of those proceedings.
In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication, arbitration or other dispute resolution procedures may then be necessary to resolve the dispute. The final certificate is then only conclusive in relation to matters that are not disputed.
If the client intends to pay a different amount from that shown on the certificate, they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (a 'pay less notice' - see Housing Grants, Construction and Regeneration Act for more information).
See also: Outturn cost.
[edit] Related articles on Designing Buildings
- Accounting.
- Campaign for cash retentions reform.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plans.
- Cost reporting.
- Cost value reconciliation.
- Defects.
- Escrow.
- Final certificate.
- Fluctuations.
- Housing Grants, Construction and Regeneration Act.
- Liquidated damages.
- Loss and expense.
- New Rules of Measurement.
- Outturn cost.
- Pre-tender estimate.
- Prime cost sums.
- Provisional sums.
- Retention bond.
- Scott schedule.
- Tender pricing document
- Variations.
- Whole-life costs.
Featured articles and news
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.



























Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.